#haharbud #budujdomusamemu #zbudujsamdom #sabudujedom
#blachypruszynski #souda #building #
Building a house using an economic system. The house is 63 m², but has a usable attic, for a total of 114 m².
COSTS:
Paperwork
Design PLN 999
Municipal Local Development Plan PLN 50
Adaptation + modifications PLN 3,000 + PLN 900
Geotechnical survey PLN 1,033
Plot preparation:
Temporary fencing PLN 550
Foundation for a metal frame PLN 500
Metal frame PLN 3,700
Foundations:
Surveyor PLN 800
Excavator PLN 800 (5.5 hours of work)
Steel
12 x 20 mm rod PLN 60 - PLN 1,200
6 x 40 mm rod PLN 10 - PLN 400
Ready-mix concrete (I got 18 m³) PLN 300 - PLN 5,400
Blocks Concrete 560 pcs. PLN 3.80 each - PLN 2,128
Sand 20t PLN 450
Cement 20 bags PLN 16 each - PLN 320
Sewer pipe 160 0.5 m - PLN 30
Arot (electricity culvert) 4m - PLN 20
Water culvert (pipes 110) - PLN 110
Gravel 2t - PLN 200
Dysperbit DN 5x PLN 75 - PLN 375
Hydrostyr 100 - 13 x PLN 148 1924
Styrofoam adhesive 7 x PLN 26 182
Backfill sand 75 tons PLN 1,300
Sewer pipes PLN 1,400
Anti-shrink reinforcing mesh 42 pcs. PLN 8 each - PLN 336
Concrete B15 - 8 m3 PLN 330 each - PLN 2640
H+H 1008 pcs PLN 14 each - PLN 14112
Thin-bed mortar 18 pcs PLN 23 each - PLN 414
Tytan foam adhesive 10 pcs xx PLN 46 each - PLN 460
Ground floor lintels - PLN 1052
2 bags of mortar - PLN 30
8m flue gas chimney + 2 vents - PLN 2600
8m flue gas chimney for fireplace + 2 vents - PLN 2616
Teriva ceiling beams + slats - PLN 8700
L-shaped collar profiles - PLN 1000
Stair formwork boards - PLN 1000
Steel for stairs 4 x 12 - 200
Support reinforcement - 504
Concrete for the ceiling 9m³ - 3150
Steel for the ring beam and separating ribs 20xØ12 - 1000
Thin-bed mortar 6x23 - 138
Ring beam:
Steel 12 pcs. Ø12 - 600
25 pcs. Ø6 - 200
Concrete B25 3.5 m³ - 1300
Wall batten 30m/b - 900
Wall batten holder 18 pcs. - 162
Rafters and collar beams - 5900
Thin-bed mortar 4xØ23 - 72
Prestressed concrete lintels 4xØ98 - 392
Concrete + steel + chemical anchor - 200
Sheet metal for the chimney 1 sheet -120
Wool - 300
Wool adhesive + mesh -120
Planitop mineral plaster -35
Membrane 3 x 300 -900
Battens 600m
Counterbattens 200m -2000
Chimney flashing 1 sheet + roofer's labor -320
Gutter strip -
Gutters (all) - 1700
Ventilation starter strip 22 pcs. - 330
Tigra metal roofing tiles, 200 sheets, -7000
Roofing flashings
Roof window + EHV-AT flashing - 1700
XDP flashing - 100
Roof hatch -300
9 windows + installation -20,000
Soudal Hybrid + LQ membranes -413
Partition walls
H+H 12 cm blocks, 4 pallets, 3000
Thin-bed mortar, 15 bags, 375
Woder XS x3, 540
Electrical installation 4500
Plaster 220m², 2432
Plumbing installation
Sewerage (pipes, elbows) 610
Sills 930
TOTAL PLN 123,287