Indirect cost loading in primavera p6.

Опубликовано: 16 Июль 2026
на канале: Engpro
1,237
14

How to add indirect cost on Primavera p6, simple method using LOE activity type into a Period of time. This is a simple method usually scheduler do when they do not have time to charge activity per activity resources and want to create a fast S-curve.

Level of Effort activities are an essential component in building complete schedules, for displaying and representing supportive, non-discrete work.

Examples of Level of Effort activities include:

Customer Meetings
Project Management
Site Management tasks
Maintenance of equipment
Clerical work

primavera p6 training full construction resources assignments.