Dangling Logic in Project Schedules
Logic Driven project schedules can suffer from two kinds of open-ended or Dangling Logic, which makes the resulting schedule unreliable for dates or float analysis.
Project schedules need robust logical bases to reach two primary objectives:
1- A schedule that accurately represents a true and achievable plan for executing the work – including technological and resource constraints.
2- A schedule that supports accurate forecasting of consequences when the work does not proceed as originally planned – for example when activities fail to start or finish on time.

Planning – P6 Channel videos Link:

   / planningp6  

50- How to use Filldown Option in primavera p6 | Copy and duplicate activities values in p6 | primavera

   • How to use Fill down Option in primav...  

51- How to Assign and Remove Multiple Resources in Primavera P6 Schedule | Multiple Activities P6 | Tips

   • How to Assign and Remove Multiple Res...  

52- How to Assign Cost Loading from Excel to Primavera P6 Import and Export | Tips and Tricks | Planning

   • How to Assign Cost Loading from Excel...  

53- How to add Assign and change Resource Rate Type in Primavera P6 | Add resource Rates in P6 | P6 |

   • How to add Assign and change Resource...  

54- How to Assign Overtime Factor to Resources in primavera P6 | Calculate overtime cost in primavera p6

   • How to Assign Overtime Factor to Reso...  

55- What is the difference between Retained Logic and Progress Override and Actual Dates in Primavera P6

   • What is the difference between Retain...  

56- How to track and trace out of sequence activities in primavera p6 | apply filter in p6 | Planningp6

   • How to track and trace out of sequenc...  

57- How to assign and change Relationships by using Excel to primavera P6 | lag and type relationships

   • How to assign and change Relationship...  

58- How to Assign and change and remove Relationship of activities from Gantt Chart in Primavera P6 | P6

   • How to Assign and change and remove R...  

59- How to Use Trace Logic In Primavera P6 | Save Layout and Print Trace Logic | Planning P6 | Projects

   • How to Use Trace Logic in Primavera P...  
60- How To Add Assign Calculate Est Weight Apply Top Down Estimation In Primavera P6 | Weightages | p6 |

   • How To Add Assign Calculate Est Weigh...  

61- How to Create Assign and filter Activity Codes in Primavera P6 | Activity codes for schedule P6 |

   • How to Create Assign and filter Activ...  

62- How to Create Assign Group and Sort Project Codes in Primavera P6 | Create Filters for Project code

   • How to Create Assign Group and Sort P...  

63- How to Renumber Activity IDs To Arrange Activities in Primavera P6 | Change Activity IDs | Tips P6

   • How to Renumber Activity IDs To Arran...  

64- How to Show Customize and Print WBS Chart View In Primavera P6 | Print Setup | P6 Tips and Tricks |

   • How to Show Customize and Print WBS C...  

65- How to do Resource Leveling in Primavera P6 | Level overallocation of Resources in P6 | Planning P6

   • How to do Resource Leveling in Primav...  

66- How to Add and create column Total Budgeted Units In primavera P6 by using Global Change option p6

   • How to Add and create column Total Bu...  

67- How to create activities in excel and import to primavera p6 | Add export activities p6 | Planningp6

   • How to create activities in excel and...  

68- How to remove individual selected multiple and all relationships from activities in primavera p6

   • How to remove individual selected mul...  

69- How to remove the schedule log file error in primavera p6 | Tips and Tricks Primavera | PlanningP6 |

   • How to remove the schedule log file e...  

70- How to extract create and generate lag report in primavera p6 | PlanningP6 | Tips and Tricks P6 | P6

   • How to Create Extract and View Lag Re...  
71- How to create and remove dangling logic in primavera p6 | Planningp6 | Logics in primavera | Tricks

   • How to create and remove dangling log...  

#danglinglogic,#relationships,#primaverap6