Penjelasan bagaimana implementasi, Step dan Membuat Value Stream Mapping (VSM)
Tentukan product family
Capture current state map
Buat Future state map
Buat Detail Action plan
Untuk lebih jelasnya, silahkan lihat video.
Koreksi :
1. Perhitungan processing time
24 sec = 0.0008 day
1 Day = 8 working hour
Processing time 0.0008=24/(8x60x60)
2. Perhitungan Takt time
Takt time = Time available/Customer demand
TT=8Jam/25Box=(8x60x60) / (25x10000)=0.11s