Pakistan’s first nuclear plant, Karachi nuclear power plant (Kanupp), is undergoing a 2,200MW capacity extension, with two 1,100MW pressurised water reactor (PWR) units of Chinese design under construction at the site.
The $10bn project is being built with financial assistance from China, the biggest energy and infrastructure investor in Pakistan.
Karachi nuclear power plant is located on the Arabian Sea coast, approximately 18km east of Karachi and has been in service with a single 137MW reactor unit (Kanupp-1) since 1972. It is owned and operated by Pakistan Atomic Energy Commission (PAEC).
Construction of the Kanupp-2 and Kanupp-3 reactor units started in August 2015 and May 2016, with the start of commercial operations scheduled for 2021 and 2022, respectively.
Reactor units will have a design life of 60 years and account for roughly 10% of the country’s total generation capacity.