How to: Material Resources in Microsoft Project

Опубликовано: 06 Апрель 2026
на канале: Dale Howard Microsoft Project MVP
921
22

Struggling with assigning material resources in Microsoft Project? Did you know there are two different methods to do it correctly? 🚀

In this video, Dale walks you through:
✅ Fixed Consumption Rate – When the material amount stays the same regardless of task duration.
✅ Variable Consumption Rate – When material usage depends on task duration.

With real-world examples like concrete for a warehouse foundation and gasoline for a cross-country road trip, you’ll see how Microsoft Project handles each scenario.

🔹 Learn how to properly assign material resources
🔹 Avoid common mistakes that could impact your project costs
🔹 Optimize your schedules with precision

📌 Like, share, and subscribe for more expert Microsoft Project tips!
💬 Have a question? Drop it in the comments below!

👉 Watch now and take control of your material assignments!

For more Microsoft Project tips and tricks check out my blog
📰 https://www.dalehowardmvp.com/microso...
 
💎Download your Quick Access toolbar for Free Here https://www.dalehowardmvp.com/free-qu...
 
✅ Download your Free Quality filters here. https://www.dalehowardmvp.com/free-mi...
 
🖋️ If you find these tips helpful, please leave a comment or if you have other topics/questions about Microsoft Project leave it in the comments.
 
✉ If you have a topic or question you would like me to create a video about you can submit your questions at https://www.dalehowardmvp.com/contact...
 
To see other people's questions and my answers over the last 20 years, here's some links for the Microsoft Project message boards.
✓ Microsoft: https://techcommunity.microsoft.com/t...
▶️ LinkedIn:   / 25618  
 
If you're looking for a full course on Microsoft Project, check out one my OnDemand courses and you can be a Schedule Hero in just a week!
 
▶️ https://www.dalehowardmvp.com/microso...
 
🌐 My Website: https://www.dalehowardmvp.com/
#MicrosoftProject #ProjectManagement #MSProject #MaterialResources #TaskManagement #ProjectPlanning #PMO #ConstructionPlanning #Microsoft365 #ProjectScheduling #ResourceManagement #DaleHoward #FixedVsVariable #ProjectTips #MSProjectTutorial