Project Development & Documentation Mock Exam Question #4 | ARE 5.0 PDD Mock Exam

Опубликовано: 21 Октябрь 2024
на канале: Black Spectacles
80
1

👇 Drop your answer - A, B, C or D - in the comments!

🔍 Scenario: The design team is approaching 100% CDs and performs an in-house QA/QC. During this session, the reviewer discovers a non-compliant condition at the straight ramp in front of the building – there is not enough length at the bottom landing. The ramp is currently 32’ long and is already at maximum slope.

What should the architect do?

A. Remove the intermediate landing to reduce the ramp length.

B. Provide a switchback landing.

C. Extend the ramp to decrease slope.

D. No action required.