Earned Value Measurement - PMP Exam

Опубликовано: 17 Июль 2026
на канале: QRSchool
500
10

In this video, we explore Earned Value Measurement (EVM), a project management technique that integrates scope, schedule, and cost data to assess project performance and progress. EVM helps measure a project's actual performance against its planned performance, enabling managers to predict future trends and make informed decisions.

TImestamps:

0:00 - Intro
0:31 - Budget at Completion
0:51 - Earned Value
1:22 - Planned Value
1:46 - Actual Cost
2:08 - Cost Variance
2:56 - Schedule Variance
3:45 - Cost Performance Index
4:45 - Schedule Performance Index
5:44 - Estimate at Completion
7:32 - Estimate to Complete
7:59 - Variance at Completion
8:39 - To Complete Performance Index
9:27 - Practice Questions

This topic covers EVM formulas of BAC, EAC, ETC, SPI, CPI, VAC, TPCI, SV, CV, EV, PV, AC.