John Muir ConFoam Pour

Опубликовано: 17 Июль 2026
на канале: The Conco Companies
1,521
12

ConFoam Pour Details

4,111 CY Total
3 Sections poured in 6 Days - Average 685 CY/DAY - Largest Single Day Pour 1,104 CY
Material Specs: ConFoam Drain 27 PCF / 40 PSI Permeable Low Density Cellular Concrete (PLDCC)
Backfill on top mat slab below slab on grade - Interstitial Space
Vapor Barrier + Rebar Installed next day
Reduced backfill duration from 3 weeks to 1 week
Minimal Impact to surrounding jobsite activities
Crew Size: 1 Hoseman, 1 Finisher

lightweight cellular concrete