The historic road bridge at Stamford Bridge has reopened two weeks ahead of schedule following an essential repair scheme.
The single-track bridge - which carries the busy A166 road between Driffield and York - reopened in time for the evening rush hour today (Friday 12 July) after eight weeks of work to strengthen the structure was completed.
East Riding of Yorkshire Council invested £350,000 in repairing the Grade II listed bridge and improving road safety, following years of damage caused by vehicles.
Built in 1727 – making it almost 300 years old – the 80m-long bridge over the River Derwent has been struck in several traffic accidents in recent years, causing severe damage to its stone parapets.
Thanks to a smooth and successful engineering project, the council’s YORhub framework contractor Esh Construction was able to complete the work ahead of its 10-week schedule.