Beam work Preparation.

After the site preparation and excavation of trenches is completed, then forms will be placed according to the dimensions of the beam which shall be provided in the design drawings.
If the grade beam is constructed on the ground, then the bottom of the form Shall be placed prior to its sides.
In this case, flat soling brick is formed along the grade beam instead of bottom shutter.
After that , either the reinforcement cage is placed on the flat soling brick is formed along the grade beam instead of bottom shutter.