AcceleratedSAP Methodology (ASAP)
Phase 1: Project Preparation
Outcomes:
Initial project timeline and scope
Architecture, products, and landscape
Resources and project team
Kick-off
Phase 2: Business Blue Print (BBP)
Outcomes:
AS-IS: Definition of current processes
TO-BE: Definition of future processes in SAP (current processes + new requirements)
Initial RICFW list - GAP analysis
Sandbox unit testing
Business Blue Print document (BBP)
Phase 3: Realization
Outcomes:
System configuration in DEV
Functional Unit Testing (FUT)
RICEFW development and testing
Data migration strategy
System Integrated testing (SIT) - configuration testing in QAS
Phase 4: Final Preparation
Outcomes:
Data migration mock test
User Acceptance Testing (UAT) - configuration + security + RICEFW testing in QAS
Change Requests
Cutover activities list
Phase 5: Go Live
Outcomes:
Production system creation (PRD)
Cutover activities execution
Updated data load
Connections with legacy systems
Go Live and support activities
LEARN MORE: www.tlpvsolutions.com