Assembly of the 2.1-miles long deck of HS2’s longest bridge – the Colne Valley viaduct – has entered the final stretch, following the completion of the final lake span.
Over 90% of the 1,000 individually pre-cast deck segments have now been installed, and all four of the lake spans completed.
Work to install the viaduct’s remaining deck segments continues at pace, followed by the installation of the deck edge parapets and noise barriers, before we hand over to Rail Systems for the next major phase of the build programme.
The huge structure – which will be stretches across a series of lakes and waterways between Hillingdon and the M25 – will be the UK's longest railway bridge, and almost a kilometre longer than the Forth Rail Bridge in Scotland.
It has been engineered to carry trains travelling at speeds of up to 200 miles per hour.
Once complete, HS2 will provide faster and far more reliable journeys between London and Birmingham, with trains running on conventional lines further north. It will also double rail capacity between the UK’s two biggest cities – relieving the most congested southern part of the West Coast Main Line, creating more capacity for local and freight services.
Find out more at: https://www.hs2.org.uk/building-hs2/v...
@bouyguesconstruction
Follow us on social media:
Twitter: / hs2ltd
Instagram: / hs2ltd
Facebook: / hs2ltd
LinkedIn: / high-speed-two-hs2-ltd
0:00 Introduction
0:13 How much progress has been made?
0:35 How does the launching girder operate?
0:56 Tensioning the viaduct segments
1:53 What works are left?
2:14 Travelling over different landscapes
2:28 The viaduct design
3:00 Outro
#HS2 #Construction #engineering #railway #dji #drone #london #train #bridge
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected].